Recharge Power takes the lead! Taipower's largest 20MW storage site in Taiwan goes live in Kaohsiung

The energy storage system at Taipower's Luyuan Substation, delivered by Recharge Power as turnkey contractor, has been completed and energized. At 20MW, it is Taiwan's first large substation storage system and will help keep Taipower's supply stable.
- The contract was won in October 2021; installation finished and power was switched on August 30, 2022, followed by trial operation
- The new-generation systems Recharge Power is bringing in offer both automatic frequency control (AFC) and enhanced control logic (E-dReg), and can also take Taipower dispatch
- Next, the company plans to start a 100MW AFC storage site at year-end, with completion expected in 2023